LAUREL STREET APARTMENTS - BARRE, VT

Naylor & Breen is currently accepting subcontractor bids for the renovation project at the Laurel Street Apartments in Barre, VT

BID DATE: September 15, 2010
BID TIME: 2:00PM

SUBCONTRACTOR BIDS DUE: September 14, 2010 @ 5:00PM

This project is TAX EXEMPT

For further information please contact Doug Gorton @ (802) 247-6527

SUBMITTED BY: Charity 8/31/10

FOREST PARK WEST

Addendums 1 & 2 have been issued for the Forest Park West bid. They do include some updated drawings.

Please contact Doug Gorton @ 247-6527 for further information.

SUBMITTED BY: Charity Eastman 7/7/10

CASTLETON FEDERATED CHURCH

Addendum #2 has been issued for the Castleton Federated Church bid.

Please contact Doug Gorton @ 802-247-6527 for more information.

SUBMITTED BY: Charity Eastman 6/24/10

FOREST PARK WEST

Naylor & Breen is currently accepting subcontractor bids for the Forest Park West project.

BID DATE: July 15, 2010
BID TIME: 2:00PM

Scope includes sitework, general construction. Sitework involves, but is not limited to, earthwork, utilities, paving & walks. New construction of 33 units of housing in 7 new structures of varying design.

This project is NOT Tax Exempt.

Please contact Doug Gorton @ 802-247-6527 for more information.

SUBMITTED BY: Charity Eastman 6/23/10

CASTLETON FEDERATED CHURCH

Addendum #1 has been issued for the Castleton Federated Church project.

Bid date and time remains the same.

Please contact Doug Gorton @ 802-247-6527 for more information.

SUBMITTED BY: Charity Eastman 6/22/10

STAFFORD TECHNICAL CTR PHASED RENOVATIONS

Addendum #2 has been issued for the Stafford Technical Center Phased Renovations project.

Bid date and time remain the same.

Please contact Doug Gorton @ 802-247-6527 for more information.

SUBMITTED BY: Charity Eastman 6/22/10

STANISLAUS HOUSING

Addendum #4 has been issued for the Stanislaus Housing project (6/21/10)

BID DATE CHANGE: July 1, 2010
BID TIME CHANGE: 10:00am

For more information, please contact Doug Gorton @ 802-247-6527

SUBMITTED BY: Charity Eastman 6/22/10

STANISLAUS HOUSING

Addendum #3 has been issued for the Stanislaus Housing Bid.

The bid date remains the same.

Please contact Doug Gorton @ 247-6527 for more information.

SUBMITTED BY: Charity Eastman 6/21/10

CASTLETON FEDERATED CHURCH

Naylor & Breen will be submitting a bid for the Castleton Federated Church.

BID DATE: June 29, 2010
BID TIME: 3:00PM

SUBCONTRACTOR BIDS DUE: June 28th @ 5:00pm

Work includes a new addition with a platform lift and stairs, toilet room renovations, new parking area and lighting of the steeple.

This project is Tax Exempt.

No addendum has been issued at this time.

For further information, please contact Doug Gorton @ 802-247-6527

SUBMITTED BY: Charity Eastman 6/18/10

STAFFORD TECHNICAL CTR PHASED RENOVATIONS

Naylor & Breen is bidding on the Stafford Technical Center Phased Renovations project.

BID DATE: June 24, 2010
BID TIME: 3:00pm

SUBCONTRACTOR BIDS DUE BY: June 23rd @ 5:00pm

The project involves phased renovations to the Electrical/Plumbing/Creative Structure Building, and the Welding, Power Mechanics, Auto Technology, and Auto Body programs in the main building.

This project is Tax Exempt. All crew members working on the project will be subject to fingerprinting and a background check.

Addendum #1 has been issued for this project.